AESO large-load connections: how Alberta allocated 1,200 MW for data centres

Alberta received over 20 GW of data centre requests. How AESO's interim 1,200 MW limit was allocated, what Phase 2 and bring-your-own-generation mean, and what to check next.

The short version

Alberta became one of North America's most talked-about data centre markets almost overnight. AESO, the province's grid operator, reported 29 proposed data centre projects totalling more than 16 GW in June 2025, rising to over 20 GW by September 2025. For comparison, those requests were far larger than what the grid could take in the near term.

The 1,200 MW interim limit

In June 2025, AESO set an interim approach: 1,200 MW of large-load connections through 2028, for loads of 75 MW and up. To qualify, projects needed municipal support, financial security and completed power-flow studies.

Phase 1 allocated all 1,200 MW to two projects with executed load contracts: GLDC Load (970 MW) and Keephills Data Centre Phase I (230 MW). A load contract is not the same as being energized.

Early access

Want an Alberta map? Join the waitlist

We're deciding whether to map Alberta next. Waitlist members get early access and a free substation shortlist.

No spam. One email when early access opens.

Phase 2 and bring your own generation

Everything else moved to Phase 2. AESO's September 2026 update said the bring-your-own-generation (BYOG) process was still being finalized, with materials expected in the fall.

Bill 8, the Utilities Statutes Amendment Act, 2025 (assent 11 December 2025), supports BYOG and developer-funded transmission upgrades. The Data Centre Regulation of June 2026 directs AESO to prioritize large data centres that bring their own generation. That is a priority rule, not a blanket requirement to go off-grid.

What this means for site selection

In Alberta, the winning site is increasingly one where you can add generation and connect to transmission: near gas supply, near 240 kV or 500 kV infrastructure, and in a municipality that will support you.

A substation on a map tells you where the grid is, not whether it has room. Only AESO and the transmission facility owner can confirm capacity and a connection date.