Where to build a data centre in Alberta: transmission, land and approvals
A practical guide to Alberta data centre sites: AESO and the transmission owners, 138/240/500 kV infrastructure, AltaLIS parcels, Crown land checks and AUC approvals.
Who runs the grid
AESO operates and plans Alberta's interconnected electric system, about 26,000 km of transmission. The main transmission facility owners are AltaLink, ATCO Electric, EPCOR and ENMAX. Your connection will involve AESO and whichever of these owns the nearby substation.
Where the transmission is
AESO's system map shows substations and 138, 240 and 500 kV lines, with the strongest corridors between Edmonton and Calgary and toward Fort McMurray. For a large data centre, start with 240 kV and 500 kV substations where several lines meet.
Early access
Want an Alberta map? Join the waitlist
We're deciding whether to map Alberta next. Waitlist members get early access and a free substation shortlist.
No spam. One email when early access opens.
Check the queue
AESO publishes a monthly connection project list, a dashboard and GIS/KML files of projects and transmission, last updated 3 November 2026. Accepted requests include active, energized and cancelled projects, so filter carefully to see who else wants the same substation.
Land
AltaLIS sells cadastral boundaries, title polygons and land identifiers; check the licence before you share the data. Use Alberta's public land search to check Crown surface dispositions and restrictions on a site. Also look at gas pipelines nearby if you plan on-site generation.
Approvals
Power plants, substations and transmission lines need approval from the Alberta Utilities Commission under Rule 007 (updated November 2025). Municipal support also counts in AESO's process, so speak to the county early.
A substation on a map tells you where the grid is, not whether it has room. Only AESO and the transmission facility owner can confirm capacity and a connection date.