Alberta, Canada · Data centres · Updated 7 November 2026

Alberta's data centre strategy, levy and bring-your-own-power rules explained

Alberta's AI data centre strategy, the levy on data centres of 75 MW and up, and the rules that favour projects bringing their own generation — plus the major projects so far.

The strategy

Alberta's AI data centre strategy (December 2024) rests on three pillars: power capacity, sustainable cooling and economic growth. It points to the province's natural resources and cold climate, which reduces how much cooling a data centre needs. In November 2026, the province's ambition of $100 billion in investment within five years was being reported — an ambition, not committed money.

The levy

After consultation in mid-2025, Bill 12 (assent 9 December 2025) created a levy framework for data centres of 75 MW and up. The government's fact sheet describes a levy of up to 2% of the value of computing equipment, a lower rate for projects with their own generation, and deductibility against Alberta corporate income tax. Check the final regulations for the exact rates and start date before you model them.

Early access

Want an Alberta map? Join the waitlist

We're deciding whether to map Alberta next. Waitlist members get early access and a free substation shortlist.

No spam. One email when early access opens.

Bring your own power

Bill 8 and the June 2026 Data Centre Regulation both favour projects that bring generation. AESO is directed to prioritize those projects and can set connection criteria and load-management rules.

Projects to know

Wonder Valley, Greenview County (O'Leary Digital): Phase 1 listed as proposed, with 1.4 GW of off-grid power and a $12 billion initial cost.

Greenlight, Sturgeon County (Pembina and Kineticor): final investment decision in July 2026 on 932 MW of gas-fired generation to supply a data centre.

Keephills (TransAlta): February 2026 agreement for about 230 MW initial supply, potentially up to 1 GW, still subject to approvals.

Beacon AI Centers: a proposed 1,494 MW plant supplying about 1,200 MW to data halls is before the Alberta Utilities Commission.

eStruxture CAL-3, Rocky View County: 90 MW, with CoreWeave as anchor tenant.

What it means

Sites near gas supply, transmission and supportive municipalities move first. A substation on a map tells you where the grid is, not whether it has room. Only AESO and the transmission facility owner can confirm capacity and a connection date.