United States · Data centers · Updated 7 November 2026

ERCOT large loads and Texas SB 6: what data center developers must do

Texas SB 6 sets new rules for loads of 75 MW and up: screening fees, site control, backup-generation disclosure and curtailment. Here's what it means for data center sites in ERCOT.

The short version

Texas is the biggest data center power market in the US by requests. ERCOT's preliminary survey published on 5 November 2026 covered 245 large loads of 75 MW or more, requesting about 166 GW in total, with 33 projects asking for more than 1 GW each. These are requests in a survey, not approved connections or a build forecast.

To manage that wave, Texas passed SB 6, effective 20 June 2025. It tells the Public Utility Commission of Texas (PUCT) to set interconnection standards for large loads.

Who is covered

SB 6 uses a threshold of 75 MW, which the PUCT may lower. If your data center will draw 75 MW or more from the transmission system, plan as if these rules apply.

Early access

Want a US site finder? Join the waitlist

We're deciding which US markets to map first. Waitlist members get early access and a free substation shortlist for their target state.

No spam. One email when early access opens.

What you will need to show

An initial transmission screening fee of at least $100,000, with more fees if you later ask for more capacity.

Proof of site control — an option, lease or ownership of the land.

Financial commitments for the transmission work, and contributions toward interconnection costs.

Disclosure of substantially similar requests elsewhere in Texas that could change, delay or cancel your application. In practice, this makes it harder to hold placeholder requests at many substations.

Backup generation and curtailment

Developers must disclose non-exporting backup generation that can serve at least 50% of on-site demand. After certain market services have been used, ERCOT may require that backup to run, or require the load to curtail. Covered transmission-connected loads interconnected after 31 December 2025 also need remote-disconnect capability for use during firm load shedding, with exceptions for critical loads.

Implementation is still being worked out: ERCOT's 2 September 2026 notice described proposed operating mechanics and draft rule changes, not a finished framework.

What it means for site selection

Because site control now comes before screening, the order of work matters: shortlist substations first, secure options on the best land next to them, then file. A site 10 miles from a strong 345 kV node can lose to a smaller parcel right next to it.

A substation on a map tells you where the grid is, not whether it has room. Only the utility or grid operator can confirm available capacity and a service date.