Where to build a data center in the US in 2026: power markets compared

Texas, Virginia, Ohio, Georgia, Arizona, Oregon, Wisconsin and Louisiana compared on what matters most for data centers: large-load queues, tariffs and power supply.

The short version

There is no single best state. Each market trades off speed, cost and contract risk differently. Here is how the main markets compare on power, the factor that decides most data center timelines.

Texas (ERCOT)

The largest pipeline: 245 large loads requesting about 166 GW in ERCOT's November 2026 survey. SB 6 adds screening fees, site-control requirements and curtailment rules for loads of 75 MW and up. Fast-moving, but competitive — strong substations go first.

Early access

Want a US site finder? Join the waitlist

We're deciding which US markets to map first. Waitlist members get early access and a free substation shortlist for their target state.

No spam. One email when early access opens.

Virginia and the PJM region

The biggest existing cluster, but the tightest supply: PJM's last two capacity auctions cleared at the price cap, and the 2027/28 auction came up 6,623 MW short. Expect long connection timelines in the busiest zones.

Ohio

AEP Ohio's data center tariff sets an 85% minimum on subscribed demand over 12 years, with financial guarantees and exit fees. Clear rules, but a firm commitment is needed.

Georgia

Georgia Power reported a 50.9 GW large-load pipeline in Q3 2025, with 11 GW committed across 28 projects. A large, active market where commitments matter more than headline pipeline numbers.

Arizona

At SRP, 24 applicants sought 7.2 GW; after initial deposits were required, that fell to three applicants seeking about 1 GW. A clear sign that deposits filter out speculative requests. Those are SRP figures; APS runs a separate process.

Oregon

Oregon's POWER Act led to PGE's Schedule 96, with cost-reflective data center rates, contract protections and responsibility for the required emissions-free supply. This applies to PGE, not every utility in the Pacific Northwest.

Wisconsin

The state regulator lowered We Energies' very-large-customer threshold to 100 MW and set 15-year minimum initial contracts in April 2026.

Louisiana

Entergy Louisiana received approval for three combined-cycle gas plants to support Meta's Hyperion data center: two in Richland Parish expected in late 2028 and one at Waterford by the end of 2029. This shows the build-your-own-supply model at scale.

How to choose

Start from where your tenant needs to be, then compare substations in two or three markets. A substation on a map tells you where the grid is, not whether it has room. Only the utility or grid operator can confirm available capacity and a service date.