PJM capacity prices and data centers: what the auction spikes mean for your site
PJM capacity prices jumped from $28.92 to $269.92/MW-day and then hit the cap twice. How data center load drives PJM's forecasts, and what it means for Virginia and Ohio sites.
The short version
PJM runs the grid for 13 states and Washington DC, including Northern Virginia, the world's largest data center cluster. PJM attributes about 30 GW of the 32 GW of extra peak demand it expects between 2024 and 2030 to data centers. Its January 2026 forecast sees summer peak demand above 222 GW by 2036.
Three auctions in a row
Capacity prices are what PJM pays generators to be available, in dollars per MW-day. They are not retail power prices, but they flow into them.
2025/26: $269.92 for most of the region, up from $28.92 the year before. The Dominion zone cleared at $444.26.
2026/27: $329.17, at the approved cap.
2027/28: $333.44, again at the cap — and PJM fell 6,623 MW short of its reliability requirement.
Early access
Want a US site finder? Join the waitlist
We're deciding which US markets to map first. Waitlist members get early access and a free substation shortlist for their target state.
No spam. One email when early access opens.
Why this matters for site choice
A tight capacity market means more pressure on utilities to make large loads pay their own way and to slow connections. In 2024, Dominion warned that some large data center hookups could take up to seven years. That was a warning at the time, not a guaranteed timeline for every Loudoun site, but it shows why power, not land, sets the schedule.
In Ohio, AEP's approved tariff requires new large data centers to pay for at least 85% of their subscribed demand over a 12-year arrangement. Expect similar terms elsewhere in PJM.
Co-location is changing
In December 2025, FERC ordered PJM to set clear rules for data centers co-located with power plants. Co-location can speed things up, but it does not automatically remove the need for grid service or the costs that come with it.
What to do
If your customer must be in PJM, look beyond the most crowded zones and compare substations by voltage, number of lines and nearby generation. Then take a short list to the utility early.
A substation on a map tells you where the grid is, not whether it has room. Only the utility or grid operator can confirm available capacity and a service date.
Sources
- PJM — Load forecasting (January 2026 forecast)
- PJM — 2025/2026 Base Residual Auction report
- PJM — 2025 annual report, markets
- PJM — 2027/2028 auction results (17 Dec 2025)
- Bloomberg — Data centers face seven-year wait for power hookups in Virginia (Aug 2024)
- FERC — Order directing PJM co-location rules (18 Dec 2025)
- AEP Ohio — Data center tariff approved (9 Jul 2025)