Dutch offshore wind and grid build-out to 2031

Year-by-year view of planned offshore wind farms, TenneT converter stations and 525 kV export cables in the Netherlands through 2031.

See Netherlands on the live grid map

Every substation, grid line and energy project. Free, no sign-up.

Open the Netherlands map →

About 10 GW in five wind farms

IJmuiden Ver Alpha, Beta and Gamma and Nederwiek 1 and 2 add about 2 GW each. TenneT connects them with 2 GW, 525 kV DC links to new converter stations at Borssele and Maasvlakte.

Timeline

2029: IJmuiden Ver Alpha (Borssele) and Beta (Maasvlakte), both with permits awarded and grid works under construction. 2030: IJmuiden Ver Gamma. 2031: Nederwiek 1 and 2. The later years are estimates.

Check this on the Netherlands map

Substations scored for BESS, solar, wind and data centers, plus land positions and instant site checks.

Why it matters onshore

Most of this power lands in Zeeland and the Rotterdam port area. Those 380 kV nodes become prime locations for battery storage, electrolysers and data centers that can soak up offshore output, but they also face long connection queues.

Track it on the map

Each item on Gridscouter shows its status and links to a TenneT, government or trade press source.

Play the 2026–2031 forecast on the Netherlands map →

Official grid capacity sources for Netherlands

Status is per area, not per plot, and says nothing about land, zoning, noise or flood risk. A 'waiting list' area can still suit a battery on a flexible or non-firm contract.