Netherlands · Forecast to 2031 · English

Dutch offshore wind and grid build-out to 2031

Year-by-year view of planned offshore wind farms, TenneT converter stations and 525 kV export cables in the Netherlands through 2031.

About 10 GW in five wind farms

IJmuiden Ver Alpha, Beta and Gamma and Nederwiek 1 and 2 add about 2 GW each. TenneT connects them with 2 GW, 525 kV DC links to new converter stations at Borssele and Maasvlakte.

Timeline

2029: IJmuiden Ver Alpha (Borssele) and Beta (Maasvlakte), both with permits awarded and grid works under construction. 2030: IJmuiden Ver Gamma. 2031: Nederwiek 1 and 2. The later years are estimates.

Why it matters onshore

Most of this power lands in Zeeland and the Rotterdam port area. Those 380 kV nodes become prime locations for battery storage, electrolysers and data centers that can soak up offshore output, but they also face long connection queues.

Track it on the map

Each item on Gridscouter shows its status and links to a TenneT, government or trade press source.

Play the 2026–2031 forecast on the Netherlands map →