Netherlands · Grid guide · English

The Netherlands wants 28 GW of batteries by 2040. Its grid fees say otherwise

A critical read of the Dutch storage policy agenda: the 110 GWh / 28 GW target is non-binding, TDTR capacity is fully allocated, high-voltage tariffs rise 20% in 2027 and no storage tariff exemption is in sight.

See Netherlands on the live grid map

Every substation, grid line and energy project. Free, no sign-up.

Open the Netherlands map →

What happened

The Dutch Ministry of Economic Affairs and Climate published the Beleidsagenda Energieopslag (energy storage policy agenda), drawn up with Netbeheer Nederland, Energy Storage NL, the regulator ACM and regional governments. The headline is 110 GWh and 28 GW of batteries by 2040, counting home, stand-alone, co-located and vehicle-to-grid batteries.

At the end of 2025 about 2.1 GWh was installed, so the target is more than fifty times today's fleet. But it is a guideline from the National Energy System Plan, not a binding target, and it can be revised. RVO will publish an annual storage monitor; if rollout falls behind, the cabinet 'should' take extra measures.

Sources: TenneT news, 8 November 2026; Rijksoverheid news, 9 November 2026; Beleidsagenda Energieopslag (pdf); ACM, TenneT 2027 tariff proposal (7 October 2026); TenneT TDTR page and grid congestion newsletter (December 2025).

The biggest problem isn't solved: grid fees

Talk to any Dutch BESS developer and you hear the same complaint: transport tariffs kill the business case. The agenda acknowledges this but offers no short-term fix. Tariffs are in fact going up.

In TenneT's 2027 tariff proposal, high-voltage (HS, 110/150 kV) transport tariffs rise about 20% on average, while extra-high-voltage (EHS, 220/380 kV) tariffs fall about 6%. ACM expects to set final tariffs in late November 2026, effective 1 January 2027. Most utility-scale batteries sit on 110 or 150 kV, so they take the increase. The proposal doesn't mention batteries.

A storage tariff exemption like those in Belgium and Germany isn't coming soon. ACM will only grant a discount if its own study shows batteries lower system costs, and it wants EU guidance on the Belgian and German exemptions first. That study is still running. Keep it out of your base case: it is more likely two or more years away than a few months.

Check this on the Netherlands map

Substations scored for BESS, solar, wind and data centers, plus land positions and instant site checks.

TDTR works, but it's sold out

Time-limited transport rights (TDTR) are currently almost the only way a large Dutch battery pencils out. You get transport at least 85% of the time and TenneT may curtail in the remaining 15%. TenneT says TDTR combined with time-dependent tariffs can save up to 65% on grid fees.

The agenda presents the roughly 6 GW of TDTR offered to batteries as progress. What it leaves out: the 9.1 GW of off-peak capacity on the high-voltage grid is fully allocated, against more than 70 GW of requests. New entrants go to the back of the line. And the ministry is exploring making a capacity-limiting contract (CSC) a condition for new TDTR contracts, which means even tighter terms for latecomers.

Flexible by default: the risk moves to the developer

Large batteries will be connected by default with a CSC and/or redispatch contract, on the principle that a battery must be grid-neutral. That makes sense for the grid, but it shifts risk onto the project: the operator can curtail you while you still pay full transport costs.

Market parties are holding back for exactly that reason, citing rising transport costs and contracts that keep changing, and asking for a fixed availability fee. Agreeing on availability fees and tariff discounts is called a 'priority', but nothing is settled. Until it is, a flexible contract is a discount on certainty, not on cost.

Permits and money: good intentions, few teeth

Permitting still differs by municipality, and Groningen, Friesland, Flevoland and Noord-Brabant each have their own siting policy. There's a chicken-and-egg problem: municipalities want grid operator confirmation first, but grid operators only know the fit late in development. The ministry is writing a guide, not a law. Battery zones around substations under the PEH II programme only arrive in 2028.

The money is modest. Flex-e has €35 million reserved for 2027, possibly with an 'XL' track — less than the cost of a single large battery park. SDE++ support is 'being explored'. Time-of-use grid tariffs reach regional grids in 2028 and small consumers in 2029, and double energy tax on home batteries is still unresolved.

Our verdict: ambition without a business case

Officially naming batteries as part of the congestion solution is a step forward. But 28 GW is a wish, not a plan. The agreements are about contracts that restrict you, permits that may get faster later and studies that are still running. The thing that actually stops projects, grid fees, does not improve in 2027.

For scale: Gridscouter's Netherlands map shows about 800 MW of operating batteries and about 2.6 GW of large projects with a target year up to 2029, plus more than 0.9 GW without a confirmed year. Getting anywhere near 28 GW needs a pipeline many times larger, and these tariffs won't deliver it.

Our base case for developers: no tariff exemption. A Dutch project works with TDTR on the EHS grid, or co-located behind an existing solar or wind connection. On the HS grid the case gets worse in 2027 unless the availability-fee talks deliver.

What to watch

Late November 2026: ACM's final 2027 tariff decision. After that: ACM's study on tariff discounts for batteries and electrolysers, the availability-fee talks for flexible contracts, the per-substation flexibility needs grid operators will publish, and the PEH II zones in 2028.

So pick the substation on voltage level and connection route first, and land second. The Gridscouter map shows each Dutch substation's voltage, the batteries already planned there and nearby solar and wind parks for a shared connection. Paid plans add cadastral plots around the station with a quick nature, flood, heritage and housing-distance check. Every Gridscouter plan starts with 14 days of full access for €0 today. Cancel before the trial ends and you pay nothing.

Gridscouter scores are estimates from open map data, not grid operator capacity figures. Always confirm capacity, contract type, tariff and connection date with TenneT or the regional grid operator.

Scout Dutch substations free for 14 days →

Official grid capacity sources for Netherlands

Status is per area, not per plot, and says nothing about land, zoning, noise or flood risk. A 'waiting list' area can still suit a battery on a flexible or non-firm contract.

Netcongestie per provincie →