Germany · Grid guide · English

Germany's battery grid queue goes points-based: TSO results due 30 November, DSO windows closing now

German TSOs announce first-cycle maturity results by end of November, while Netze BW, Bayernwerk, E.DIS and SH Netz run their own points systems. Costs, criteria, deadlines, and why flexible connections cut BESS revenue by up to 29%.

See Germany on the live grid map

Every substation, grid line and energy project. Free, no sign-up.

Open the Germany map →

The short version

First come, first served is over for large batteries in Germany. The four transmission system operators (TSOs) will tell applicants by 30 November 2026 who gets a connection reservation offer from the first cycle of their maturity procedure (Reifegradverfahren). At the same time, big distribution operators have launched their own points systems, with deadlines closing right now.

What wins capacity is no longer the date you applied, but proof of land, permits and willingness to be flexible.

Sources: TSO procedure documents (April 2026); Netze BW (August 2026); Bayernwerk Netz, E.DIS Netz and SH Netz procedure description v1.1 (12 October 2026); FairNetz (20 August 2026); Regelleistung Online via ESS News (19 November 2026); Bundesnetzagentur storage request figures for 2025.

The scale: 573 GW requested, 54 GW approved

In 2025 German grid operators received more than 18,000 battery connection requests totalling about 573.5 GW, and approved 54.2 GW. Since 24 December 2025 storage is no longer covered by the processing deadlines of the power plant connection ordinance, and the regulator confirmed in 2026 that applicants have a right to connect to the grid as it is, not a right to grid expansion.

For context, our Germany map shows around 280 battery sites today. Requests outnumber what exists many times over, which is why operators are moving to points.

Check this on the Germany map

Substations scored for BESS, solar, wind and data centers, plus land positions and instant site checks.

Transmission: what happens by end of November

50Hertz, Amprion, TenneT and TransnetBW have allocated extra-high-voltage connections for large batteries, data centres and electrolysers in cycles since 1 April 2026. The first application window closed on 30 June, with a €50,000 fee per application.

Applicants who receive an offer have one month to accept it and must post a €1,500/MW realisation deposit, so €150,000 for 100 MW. A reservation is not a connection contract and the earliest connection date is non-binding. If you are rejected in full or in part, read the reasoning carefully and strengthen the project for the next cycle.

The storage association BVES wants a separate procedure for storage instead of competing with pure loads. That debate is open but does not affect this cycle.

Distribution: the windows open now

Netze BW (Baden-Württemberg): applications from 1 November to 31 December 2026 for projects from 950 kW and every stand-alone battery. Up to 100 points: project maturity up to 50 (land 16, permit or proof no permit is needed 19, status at the transfer station 15), location-bound 34, the rest for timing. Allocation around 1 March 2027. Netze BW has more than 20 GW of open high-voltage requests against 7.3 GW peak load, over 90% of them batteries.

Bayernwerk Netz, E.DIS Netz and SH Netz (E.ON group): a joint pilot for batteries from 300 kW and loads from 1,000 kW. Registration and a €1,500/MW deposit by 23 November 2026, results by 15 March 2027. Points reward project maturity, co-location with renewables, a flexibility commitment and fit with the regional grid scenario.

Smaller utilities follow. FairNetz in Reutlingen ran its first window from 19 October to 6 November, with about 125 MW of battery requests against a total network load of about 141 MW.

The catch: flexible connections cost revenue

Almost every procedure rewards accepting a flexible connection agreement (FCA). A new calculator from Regelleistung Online compares the FCA terms of eight operators: for two-hour batteries revenue falls by 15% (N-Ergie) to 29% (Bayernwerk); for four-hour systems by 11% to 20%.

Typical terms restrict the power band when nearby wind and solar output is high, cap ramp rates and limit balancing capacity. Model the specific operator's FCA before you commit to it in an application.

What to do now

Secure land and document permit status: these carry the most points everywhere. Favour sites next to existing assets or co-located with a wind or solar park. Keep every operator's window in your calendar, because missing one usually means waiting a year.

On the Gridscouter map you can see each substation's voltage level, existing and planned batteries, and nearby wind and solar parks for co-location. Subscribers can search for suitable plots around a substation and screen them for protected areas and other exclusions.

Gridscouter scores are estimates from open map data, not grid operator capacity figures. Always confirm capacity, procedure, deadlines and costs with the grid operator.

Scout German substations free for 14 days →

Official grid capacity sources for Germany

Formats differ per operator, and large battery queues mean published headroom is often already reserved.