Permitting solar, wind and batteries in France: a developer's checklist
The main checks for solar, wind and battery projects in France: Natura 2000, flood risk, heritage, noise and grid connection with RTE or Enedis.
See France on the live grid map
Every substation, grid line and energy project. Free, no sign-up.
Open the France map →Start with the land
Check Natura 2000 areas, flood zones, heritage sites, distance to homes and access roads before you talk to landowners. Gridscouter's land check covers several of these on one click.
Grid connection
Connection requests go to Enedis for distribution voltages or RTE for transmission. Regional plans for renewable connection (S3REnR) set the capacity reserved per area.
Check this on the France map
Substations scored for BESS, solar, wind and data centers, plus land positions and instant site checks.
Local acceptance
Wind projects in particular face long reviews and appeals. Early contact with the municipality helps.
Note
This is general guidance, not legal advice. Always confirm with local authorities.